Toshiba Corporation (Tokyo: 6502) today held a groundbreaking ceremony
in readiness for the start of construction of Phase 2 of Fab 5, the
company's state-of-the-art fabrication facility (fab) at its Yokkaichi
Operations memory production facility in Mie Prefecture.
Toshiba will expand Fab 5 to secure manufacturing space for NAND flash
memories fabricated with next generation process technology and for 3D
memories. Construction will be completed in summer next year, and
decisions on equipment investments and production levels will reflect
market trends.
Three fabs at Yokkaichi Operations currently mass produce NAND flash
memories, including Fab 5 phase 1. Fab 5's construction was planned
around two phases, the first of which went into operation in July 2011.
After giving careful consideration to the balance of product supply and
demand, and noting a recovery driven by growing demand for smartphones,
tablets, SSD for enterprise servers, Toshiba now anticipates further
medium- to long-term market expansion and recognizes that the time is
right to expand Fab 5.
Going forward, Toshiba will expand business and boost competitiveness by
leadership in advanced process technology and the development of new
generation memories that answer market needs.
Outline of Fab 5
|
Structure of building:
|
|
2-story steel frame concrete, five floors
|
|
Ground area:
|
|
Approximately 38,000m2
|
|
Total floor area:
|
|
Approximately 187,000m2
|
|
Start of Construction:
|
|
First Phase:
|
July 2010
|
|
|
Second Phase:
|
August 2013
|
|
Completion:
|
|
First Phase:
|
March 2011
|
|
|
Second Phase:
|
Summer 2014 (target)
|
|
Start of Production:
|
|
First Phase:
|
July 2011
|
|
|
Second Phase:
|
To be determined later; intended primarily for technology transition
of existing wafer capacity
|
Outline of Yokkaichi Operations
|
Location:
|
|
800, Yamanoisshiki-cho, Yokkaichi, Mie Prefecture
|
|
Established:
|
|
January 1992
|
|
General Manager:
|
|
Tomoharu Watanabe
|
|
Employees:
|
|
Approximately 5,200 (as of end of March, 2013, regular
employees of Toshiba)
|
|
Site area:
|
|
Approximately 436,800 m2 (including Fab 5)
|
|
Total floor area:
|
|
Approximately 647,000m2 (including Fab 5)
|